Calico Resources USA Corp. – Grassy Mountain

 

Permitting Process Overview

There are 10 key steps to the permitting process (see sidebar).

Where is the Calico Grassy Mountain project in the process?

To submit a Consolidated Application, the first 4 steps must be completed:
Step 1. Notice of Intent to submit a Consolidated Application (Complete)
Step 2. Notice of Applicant's Readiness to Collect Baseline Data. (Complete)

Step 3. Collection of baseline data. (HAPPENING NOW)
Step 4. Filing of a Consolidated Application including: operating plan, baseline data, reclamation & closure plan, alternatives analysis.

The review and permitting process for the Consolidated Application includes Steps 5-10 as shown in the following flow diagrams. Click here to display a larger flowchart in PDF format (2 pages).

The permitting process provides multiple opportunities for the public and interested stakeholders to participate in reviewing and commenting on Calico's application and the consolidated permit requirements.

 

(last updated 12/19/2018)

 